Hartlepool Hospital – Aseptic Suite

Introduction

The University of Hartlepool has 334 beds, serving 147,500 people living in Hartlepool and the southern part of East Durham. It provides a wide range of specialities, including accident and emergency, general medicine, surgery and urology, orthopaedics, rheumatology, obstetrics and gynaecology and paediatrics.

Data

Industry Sector: Aseptic Suite
Cleanroom Classification: Class 10,000/100
Grade C/B
Value: £109,000
Time on Site: 8 weeks
Physical Size: 68m2

Scope of Work

CDC Cleanroom Specialists were employed as principal contractors and designers for a complete design and build turnkey cleanroom facility incorporated:

• Partitioning
• Ceiling
• Vinyl floor
• Strip-out
• Builder’s work
• Air conditioning plant
• Automatic controls
• Electrical and lighting
• Mechanical pipework and ductwork
• Commissioning and Validation