IVF Facility

Introduction

Secured through competitive tendering and negotiation, CDC was engaged as a specialist subcontracting partner to fully design, install, commission, and successfully validate this state-of-the-art IVF cleanroom and laboratory suite ensuring the facilities remain at the cutting edge of reproductive technology.

Delivered on time and meeting all critical regulatory compliance requirements the facility fit-out included specialist cleanroom wall finishes to line out the building and segregate internal areas. Sealed panel ceilings, vinyl and resin floors, and high-specification GRP doors complement the overall architecture.

Data

Industry Sector:
Classification:

IVF Facility
Grade C (ISO 7),
Grade D (ISO 8)
Associated support rooms

Value:
Time on Site:
Physical Size:

£385,000.00
8 weeks
160m² cleanroom fit out

Scope of Work

• Strip out of existing cleanroom and mechanical services
• GRP Doors
• Vinyl flooring
• Cleanroom furniture
• Air Handling Units and Air Conditioning Units
• Supply & extract ventilation systems (Galvanised and PVC ductwork)
• Thermal insulation to mechanical services
• Cleanroom wall partitioning and suspended ceiling
• Electrical services inc new DB’s, small power, single and 3-phase, lighting, data/telecom

• Medical gases incl. compressed air, nitrogen, and vacuum
• HEPA filters, housings, and grilles
• Cryo Store and Cryo Extract
• Process chilled water system
• Domestic hot and cold-water services
• Above ground drainage pipework
• Water treatment
• Steel flooring
• Gas Detection System
• Validation and commissioning
• Production of health & safety file including O&M’s

Get in touch with us